TDG pegs Shasta gold-silver build at $605M

View of Shasta gold-silver project in BC. Credit: TDG Gold.

TDG Gold (TSXV: TDG; US-OTC: TDGGF) has drawn up a plan to mine two gold and silver deposits in northern British Columbia, days after agreeing to sell a majority stake in a nearby property to Freeport-McMoRan (NYSE: FCX).

The first preliminary economic assessment (PEA) for Shasta and Mets puts the upfront cost of two open pits and a shared mill at $605 million (US$423 million). The deposits, in the Toodoggone district about 430 km northwest of Prince George, would produce 71,200 oz. of payable gold and 2.82 million oz. of payable silver a year over 9.9 years.

“The PEA defines what we can evaluate economically today,” Paul Geddes, TDG’s senior vice-president of business development and strategy, said Tuesday in a release. “It does not define the limits of a mineralized district.”

TDG would keep both deposits and collect $110 million in cash if the Aurora West sale closes. For an explorer that put its cash at about $2 million when it announced the deal, that would pay for more drilling and engineering at Shasta. Building the mine would take considerably more capital.

TDG shares slipped 2.7% to close at 72¢ in Toronto on Tuesday, valuing the company at about $200 million.

One mill

Silver would account for 36% of gross metal revenue over the life of the operation at the study’s prices of $50 per oz. silver and $3,550 per oz. gold, both in U.S. dollars. TDG estimates an after-tax net present value of $1.18 billion, using a 5% discount rate, and an internal rate of return of 39%. Cutting both prices by a fifth brings the estimated value down to $703 million and the return to 27%.

Shasta would feed a 4-million-tonne-a-year mill, with higher-grade material from Mets added in years four and five. The plan includes inferred resources that would need further drilling and study before they could be considered for a reserve.

The Nov. 17 resource estimate gives Shasta indicated resources of 17.12 million tonnes at 0.87 g/t gold and 31.73 g/t silver, containing 479,000 oz. of gold and 17.46 million oz. of silver. Inferred resources total 26.84 million tonnes at 0.47 g/t gold and 20.57 g/t silver, for 406,000 oz. of gold and 17.75 million oz. of silver. Higher metal-price assumptions helped bring more low-grade material into the modelled pit.

Mets’ first estimate shows inferred resources of 530,000 tonnes at 2.47 g/t gold and 0.1 g/t silver, containing 42,000 oz. of gold and about 2,000 oz. of silver.

Noncore sale

The Freeport deal still needs TSX Venture Exchange approval. Freeport has committed to spend at least $30 million on exploration in the three years after closing. That counts towards the $80 million in exploration spending required to raise its stake in the main joint venture to 75%. Exercising the option would also require Freeport to pay TDG another $40 million in cash for full ownership of two separate claims. TDG would retain a 2% net smelter return royalty on those claims.

At Shasta, TDG expects the proposed development to need both a provincial environmental assessment certificate and a federal impact assessment decision.

One issue for regulators is Jock Creek, which the mine plan would divert in year four. That would require separate authorization under the federal Fisheries Act.

Print

Be the first to comment on "TDG pegs Shasta gold-silver build at $605M"

Leave a comment

Your email address will not be published.


*


By continuing to browse you agree to our use of cookies. To learn more, click more information

Dear user, please be aware that we use cookies to help users navigate our website content and to help us understand how we can improve the user experience. If you have ideas for how we can improve our services, we’d love to hear from you. Click here to email us. By continuing to browse you agree to our use of cookies. Please see our Privacy & Cookie Usage Policy to learn more.

Close